Draw PERT network for the following table and calculate (i) Expected time and variance for each...
Question:
Draw PERT network for the following table and calculate:
(i) Expected time and variance for each activity.
(ii) Probability f completing the project in 32 days.
(iii) Total project duration.
(iv) Critical path.
Activity | Estimated time (days) | ||
---|---|---|---|
To | Tm | Tp | |
1-2 | 2 | 5 | 8 |
1-3 | 1 | 4 | 7 |
2-3 | 0 | 0 | 0 |
2-4 | 2 | 4 | 6 |
2-6 | 5 | 7 | 12 |
3-4 | 3 | 5 | 10 |
3-5 | 3 | 6 | 9 |
4-5 | 4 | 6 | 10 |
4-6 | 2 | 5 | 8 |
5-6 | 2 | 4 | 6 |
Pert Network:
The Pert network is used to analyze the duration of any project. Its calculation is based on three-time estimations. The Pert method gives the variance and estimation time between the two activity points for a project.
Answer and Explanation:
Become a Study.com member to unlock this answer! Create your account
View this answer
Given data
- The project scheduled time is: {eq}{T_s} = 32\;{\rm{days}} {/eq}
(i)
The expected time for the activity 1-2 is as follows,
{eq}\beg...
See full answer below.
Ask a question
Our experts can answer your tough homework and study questions.
Ask a question Ask a questionSearch Answers
Learn more about this topic:

Get access to this video and our entire Q&A library
Related to this Question
What is a PERT in terms of business?
The optimistic cost for a project is $6,000. The...
Describe two possible job applications for a PERT...
Given is a PERT project network diagram as shown...
The project information for the custom order...
A large eastern city is requesting federal funding...
A plant engineering group needs to set up an...
It has been said that a key difference between...
The project information for the custom order...
The Sun River beverage company is a regional...
The following table of probabilistic time...
Given the following information, you are to...
Explore our homework questions and answers library
Browse
by subject