Dummy activity in a PERT network allows us to a- Specify the positive time and resources...

Question:

Dummy activity in a PERT network allows us to

a- Specify the positive time and resources required to complete the activity.

b- maintain the precedence relationships.

c- add more starting nodes.

d- add more ending nodes.

PERT

Program evaluation and review technique (PERT) is a technique adopted by organizations to analyze and represent the activity in a project, and to illustrate the flow of events in a project. PERT is a method to evaluate and estimate the time required to complete a task within deadlines.

Answer and Explanation: 1

Become a Study.com member to unlock this answer! Create your account

View this answer

Given Information:

Dummy activities in a PERT network

(b).maintain the precedence relationships

Dummy activities often have a zero completion...

See full answer below.


Learn more about this topic:

Loading...
PERT Analysis & Project Completion

from

Chapter 14 / Lesson 7
8.7K

Time-based decision methods are used a great deal when a manager or company looks at a time-based project. To ensure the project can be done on time, managers use PERT analysis, a tool for estimating the time it will take to complete a project. This lesson will outline PERT and help you to understand how it is used to predict time based projects.