Given is a Project with network diagram and activity times as shown below.

ActivityABCDEFGHIJ
Time(Weeks)55716915125118

a) The Earliest Start (ES) time of Activity I =_ weeks.

b) The Latest Start (LS) time of Activity B = weeks.

c) The Slack time of Activity C = weeks.

Slack time:

Slack time refers to the time taken to delay a task without causing any delay in another task. The delay caused does not impact the data at which the project has to be completed. It is concerned with the time a project is completed.

Answer and Explanation:

Become a Study.com member to unlock this answer! Create your account

View this answer

See full answer below.


Learn more about this topic:

Loading...
How to Calculate Slack Time

from

Chapter 9 / Lesson 18
28K

After completing this lesson, you'll understand what slack time is and how it's calculated. You'll also see why knowing your slack time is important when it comes to finishing a project on schedule.


Related to this Question

Explore our homework questions and answers library