Critical Chain Project Management: Definition & Example
What Is Critical Chain Project Management?
Have you ever tried to run a project that just did not go as planned? Learn how to avoid some issues when it comes to scheduling.
Critical chain project management is a scheduling method that plans and manages projects with a focus on allowing for resource delay. Resources can include internal and external personnel (contractors or customers), physical space, logistics, and equipment.
Critical chain project management looks at the schedule and then includes resource availability to see how that will affect the activities and project completion. Think of walking on a road. You might be walking on it at a steady pace, but if your cement supplier is bringing cement to finish the road, you will be delayed. The resource caused the delay, not the task.
Dr. Eli Goldratt developed critical chain methodology in 1997 in his book Critical Chain. Dr. Goldratt developed this method due to numerous projects having issues with extended durations on activities, missed deliveries, and budget overruns.
When an activity's duration is overestimated there are tendencies for workers to fall into student syndrome (procrastinating), Parkinson's Law (spreading out the tasks to meet the time allotted) or cherry picking tasks. If the project falls into these traps, any buffer or cushions that were built in quickly disappear.
Steps in Critical Chain Development
There are six steps that a project manager who uses critical chain project management will have to follow. Let's say that Judy is a project manager planning a project.
1. Determine Aggressive Estimates
Judy always keeps her contracted delivery dates at the forefront of her mind. To help fight off procrastination or the effects of Parkinson's Law, the project manager will determine activity durations that are aggressive. Some recommend that the normal activity time allotted should be reduced by 50%, (though some consider that too aggressive and not obtainable).
2. Create the As Late As Possible Schedule
Judy will use scheduling software to create a schedule that works backwards from the completion date through each activity, each starting on the latest possible start date. This is in contrast to the standard practice of starting as early as possible. This tactic will install a sense of urgency in the project team and have them perform at the best of their abilities.
3. Determine the Critical Chain
Judy will determine which set of activities that, if delayed, will extend the end date of the project. She will determine this based off of resource availability. All tasks not in the critical chain are part of a feeding chain.
4. Decide Where Buffers Should Go
Here Judy will decide where buffers should be placed in the schedule. Buffers can be one of three types:
- A project buffer is a single buffer added to the whole schedule, between the last activity and the ultimate deadline.
- Feeder buffers are placed in between the last tasks from the feeding chain leading to critical chain activities.
- Resource buffers are artificial buffers that make up for possible fluctuations in resource availability.
5. Determine Buffer Sizes
Here Judy will add appropriate buffer size (cushion) to activity durations. It is recommended that a cushion proportionate to the activity uncertainty or risk be included. This means that a more uncertain an activity is, the larger the buffer built in.
6. Add the Buffers to the Schedule
When Judy adds the buffers to the schedule, she creates a buffered schedule she can use to manage the critical chain project.
How to Use Critical Chain
Judy will begin to use the critical chain project management during the planning phase. She will investigate what personnel and resources are needed for the project by discussing with the managers the project's needs, including resources required.
She will make sure to include the buffers and cushions for duration. Not all resources will be available when needed or requested, so it's best to look for alternatives if an issue arises. For example, if the shop crane is unavailable during first shift, but free during second shift; Judy will see about using the crane during second shift.
During execution Judy must look ahead to what resources are needed and re-confirm their availability and commitment. Flawless execution will help the project come in on time and under budget.
Critical Chain in Action
Ley's say Sean is the project manager for the creation of a 24 hour lemonade stand. As Sean is planning his project, he creates a schedule and then evaluates the resources he needs. Two of them have a high probability of being late. The first is Johnny, an electrician who does not have the best track record for showing up on time, and tends to procrastinate. The second resource is the lemons. The weather has been bad lately and trucks are not making deliveries on time.
Sean makes sure to reduce the time he think it will take the electrician by half to avoid Johnny procrastinating, but also adds a few days of buffer that activity in case he's late. As the project moves to execution, Sean keeps in contact with Johnny and lets him know that he will be needed in a few days. The day before Johnny is to arrive; he calls Sean and says he will be a day late. The extra days built in paid off.
Sean can slide any extra days not used in the electrician activity to the lemon delivery duration (adding more cushion). Sure enough, the delivery was 6 days late due to weather. The cushions worked and Sean delivered the project on time.
Lesson Summary
Critical chain project management focuses on resources delays being factored into a project schedule. It also tends to eliminate student syndrome, Parkinson's law, or cherry picking tasks that comes from older methods of scheduling. Critical chain project management has six steps:
- determine aggressive time estimates
- construct a schedule based on late starts
- determine critical chain
- figure out where buffers are needed using
- a project buffer - a single buffer added to the whole schedule,
- feeder buffers - buffers from the feeding chain to the critical chain, and
- resource buffers - buffers in case of resource delays.
- determine amount of cushion
- add the buffers to the schedule
To unlock this lesson you must be a Study.com Member.
Create your account
Register to view this lesson
Unlock Your Education
See for yourself why 30 million people use Study.com
Become a Study.com member and start learning now.
Become a MemberAlready a member? Log In
BackCritical Chain Project Management: Definition & Example
Related Study Materials
- TExES Science of Teaching Reading (293): Practice & Study Guide
- Next Gen NCLEX-PN Study Guide & Practice
- Next Gen NCLEX-RN Study Guide & Practice
- TExES Core Subjects EC-6 (391): Practice & Study Guide
- TExES School Counselor (252): Practice & Study Guide
- Multithreading, Networking & Machine Learning in Python
- Digital Forensics
- The Internet of Things and Networking
- Network Routing and Switching
- Virtual Servers and Networking
- How to Pick Your Homeschool Curriculum
- Role of Student Support in Open & Distance Learning
- TExES Principal Exam Redesign (068 vs. 268)
- Teacher Salary by State
- ESL Resource Guide for Teachers
- What is a Homeschool Co-op?
- How to Start Homeschooling Your Children
Latest Courses
- Chemical Nomenclature & Notation
- Factors Impacting Family & Consumer Sciences
- Heritability Coefficient
- Major Health Problems in the United States
- Direct Impact of Two Smooth Bodies
- Transistor as an Amplifier & Oscillator
- Using Research to Select Interventions in Social Work
- What are Dinosaurs Related to? - Quiz & Worksheet for Kids
- Quiz & Worksheet - Memory Hole in 1984
- Finding a Character's Emotions by Actions: Quiz & Worksheet for Kids
- Quiz & Worksheet - Types of Personality Disorders
- Flashcards - Real Estate Marketing Basics
- Flashcards - Promotional Marketing in Real Estate
- Essay Topics for Teachers
- ESL Teaching Strategies for ESL Students
Latest Lessons
- AP Chemistry Syllabus Resource & Lesson Plans
- Managing a Virtual Team
- US History: Credit Recovery
- Anatomy & Physiology for Teachers: Professional Development
- Marketing: Skills Development & Training
- Strategic Management and Managerial Decision Making: Help and Review
- AP Physics 1: Mechanical Waves
- Quiz & Worksheet - Tablespoons to Grams Conversion Practice
- Quiz & Worksheet - Volume & Cavalieri's Principle
- Quiz & Worksheet - Human Capital's Importance to An Organization
- Quiz & Worksheet - Copyright Laws
- Quiz & Worksheet - Characteristics of Zip Drives
Popular Courses
- Common Appraisal Methods 1: Critical Incident, Graphic Rating Scale & BARS
- Alkenyl Halide: Structure, Synthesis, Reactions & Examples
- How to Pass 6th Grade
- What is Dual Credit?
- 7th Grade Life Science Projects Ideas
- USMLE Step 1 Preparation
- 4th Grade Science Projects
- What is the New SAT?
- How Hard is the CSET Math Exam?
- How to Pass a Chemistry Test
- What is the International Baccalaureate Primary Years Program?
- How to Pass the Police Exam
Popular Lessons
Math
Social Sciences
Science
Business
Humanities
Education
History
Art and Design
Tech and Engineering
- Tech and Engineering - Videos
- Tech and Engineering - Quizzes
- Tech and Engineering - Questions & Answers