Schedule Variance: Definition, Formula & Calculation
The Game Plan
Carlos is a real estate mogul who recently purchased two small apartment complexes. One is a small one-level complex with only 25 units and the other is much larger, with three levels and a total of 475 units. Before Carlos begins leasing to tenants, he wants to do some renovations to give his complexes a more modern look. After several discussions, Carlos and Al, the contractor, finally agree on the following schedule and budget for the renovations:
![]() |
After two months of renovations, Carlos decides to check in on Al to see how the renovations are going. Carlos wants to make sure that the renovations are on track to be completed on schedule and on budget. Al gives Carlos the following report:
![]() |
But these numbers alone are not enough to tell Carlos the status of each project. He needs to calculate the schedule variance. The schedule variance is a status update that indicates how much ahead of, behind, or on schedule a project is based on how much work has been done and how much of the budget has been spent.
The Formula
To determine the schedule variance, Carlos will need to calculate the difference between the earned value, which is what the project is worth at its current stage of completion, and the planned value, which is what the project is worth based on how much work should be completed. The formula looks like this:
Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV)
Once the planned value is deducted from the earned value, the remaining value reveals whether or not the project is ahead of or behind schedule. A positive schedule variance means the project is ahead of schedule, while a negative schedule variance means that a project is behind schedule. If the schedule variance is zero, the project is on schedule. But this doesn't tell us just how far ahead or behind we are, so let's take it a step further.
Using the schedule variance, Carlos can also calculate to what degree a project is ahead of or behind schedule by dividing the schedule variance by the planned value. The resulting percentage represents just how much the project is ahead of, behind, or on schedule.
Percentage of Schedule Variance (SV%) = (Schedule Variance (SV) / Planned Value (PV)) * 100
Similar to the schedule variance itself, a positive schedule variance percentage reveals to what degree a project is ahead of schedule, while a negative schedule variance percentage reveals to what degree a project is behind schedule. A value of zero indicates that a project is going as planned and on schedule. Let's see these formulas in action.
Plugging In the Numbers
Carlos is using the information below to calculate the schedule variance and the percentage of the schedule variance.
![]() |
To calculate the schedule variance of the one-level complex, Carlos will deduct the planned value of $50,000 from the earned value of $56,250, leaving a schedule variance of $6,250.
SV = $56,250 - $50,000
SV = $6,250
The positive value lets Carlos know that the renovations on the one-level complex are ahead of schedule. Now Carlos just needs to know how far ahead of schedule Al is with those renovations. Carlos can do this by diving the schedule variance by the planned value.
SV% = ($6,250 / $50,000) * 100
SV% = 0.125 * 100
SV% = 12.5%
Al is 12.5 percent ahead of schedule on the renovations for the one-level complex.
To calculate the schedule variance for the three-level complex, Carlos will deduct the planned value of $100,000 from the earned value of $75,000, leaving a schedule variance of -$25,000.
SV = $100,000 - $75,000
SV = -$25,000
The negative value indicates that the renovations for the three-level complex are behind schedule. Being behind schedule is never good news for Carlos and he now wants to know how far behind the renovations are for the three-level complex.
SV% = (-$25,000 / $100,000) * 100
SV% = -0.25 * 100
SV% = -25%
Al is behind schedule on the renovations for the three-level complex by 25 percent.
Carlos can use these figures to ensure projects stay on track or make any necessary changes to get projects back on track.
Lesson Summary
One of the primary goals with any project is to finish as scheduled and on budget, but this does not always happen. Schedule variance is a calculation of a project's status. It indicates whether a project is ahead of, behind, or on schedule. The schedule variance can then be used to determine to what degree a schedule is ahead of or behind schedule by calculating the percentage of schedule variance. Monitoring the status of a project helps to keep the project on track or create an awareness of needed changes.
To unlock this lesson you must be a Study.com Member.
Create your account
Register to view this lesson
Unlock Your Education
See for yourself why 30 million people use Study.com
Become a Study.com member and start learning now.
Become a MemberAlready a member? Log In
BackResources created by teachers for teachers
I would definitely recommend Study.com to my colleagues. It’s like a teacher waved a magic wand and did the work for me. I feel like it’s a lifeline.